Lesson
15

Unclear scope

Success Problem

The preparation of new project has started before signing of contract. Unfortunately the contract was not signed, sales and customer decided to make only an addendum to the existing service contract instead. Contract documents were elaborated well, but were not valid, thus the addendum was too short and vague.

Impact

waste of time, work and money – we had to rebuild some of the already delivered products, budget increased

Recommendation

do not start a project without clear scope (in some corporates not possible)

Category

0 Comments

Forgot Password?

Don’t have account? Register here!

Please read the Terms of Use and Privacy Notice

User Agreement:
Check here to indicate that you have

We have sent an email with a confirmation link to your email address. In order to complete the registration, please click the confirmation link.

The link expires within the next 14 days.

Please check, whether the email is in the junk folder, since confirmation mails with backlinks are sometimes classified as spam.

Please press the button.
Save All Changes.